Sewer System Improvements

Completed Plant Projects

The City of Valdosta Utilities Department has been working diligently on multiple wastewater system improvements.

Since 1992, the city has received $179 million in Special Purpose Local Option Sales Tax (SPLOST) funds and invested in capital improvement projects (CIP). During the same timeframe, the city has expended $167 million for water/wastewater projects from SPLOST proceeds, system revenues, bonds, and Georgia Environmental Finance Authority (GEFA) loans.

In November 2019, the SPLOST VIII was approved by voters and is expected to generate about $134 million, of which Valdosta will receive an estimated $65 million. Nearly 60 percent of the funding will be dedicated to wastewater projects, which is $40 million. Over the next 4 years, projects that will be funded by SPLOST, system revenues, GEFA loans, etc. include:

  • EPD Sewer Collection System Requirements
  • Lift Station Replacement
  • Sewer Collection Smoke Testing
  • Water Transmission System
  • Water Main Extension
  • Manhole Rehab
  • Water Plant Generator
  • Well Rehabilitation 
  • Treatment Plant Basin Resurfacing
  • Water Treatment Plant II or Loop
  • Emergency Repairs
  • GEFA Debit Reduction
  • AMI Debt Service

SEWER SYSTEM UPGRADE PROJECTS

Completed Projects

Date Completed

 

2-Mile Branch: 3,395 LF / 17 MHs

June 2020

Jerry Jones (2-Mile Branch): 285 LF

Mar 2020

Sustella Ave Creek Crossing Upgrade

July 2020

Rogers Lift Station Force Main Extension

May 2021

1-Mile Branch Sewer Upgrade (Section 3)

Nov 2021

Current Projects

Estimated Completion

Inner Perimeter Road Sewer Extension

Dec 2021

Aerial Sewer Main Reroute

Dec 2021

Future Projects

Estimated Completion

1-Mile Branch Sewer Upgrade (Sec 4)

Nov 2022

1-Mile Branch Sewer Upgrade (Sec 5)

Nov 2023

Knights Creek Sewer Upgrade (Sec 1)

Nov 2024

CURED-IN-PLACE PIPE (CIPP) LINING PROJECTS 

Completed Projects

Date Completed

 
 

CIPP #10: 1,882 LF

Oct 2020

Future Projects

Estimated Completion

CIPP #11

TBA

CIPP #12

TBA

CIPP #13

TBA

CIPP #14

TBA

 

MANHOLE REHAB PROJECTS 

Completed Projects

Date Completed

  

Current Projects

Estimated Completion

Phase 7: 35 MHs

TBA

Future Projects

Estimated Completion

Phase 8: 30 MHs

TBA

Phase 9: 30MHs

TBA

Phase 10: 30 MHs

TBA

LIFT STATION REHAB PROJECTS 

 
 

LIFT STATION GENERATOR PURCHASE/INSTALLATION PROJECTS 

Completed

Date Completed

  

ADDITIONAL PROJECTS

CURRENT SEWER STUDY & MODELING PROJECT

 

SEWER FLOW MONITORING – PHASE 1 (MUD CREEK SYSTEM)

            Status: In Progress

            Estimated Completion: April 2021

 

SEWER FLOW MONITORING – PHASE 2 (WITHLACOOCHEE SYSTEM)

            Estimated Completion: April 2022

 

HYDRAULIC FLOW MODEL UPDATE (BOTH SYSTEMS)

            Status: In Progress

Estimated Completion: June 2022

 

CURRENT SEWER INSPECTION PROGRAMS

MANHOLE INSPECTION PROGRAM

            Status: In Progress

            Estimated Completion: Continuous

 

CLEANOUT INSPECTION PROGRAM

            Status: In Progress

Estimated Completion: Continuous

            Phase 1: 2022

            Phase 2: 2023

            Phase 3: 2024

            Phase 4: 2025

            Phase 5: 2026

 

CREEK CROSSING INSPECTION PROGRAM

            Status: In Progress

Estimated Completion: Continuous

 

CCTV INSPECTION PROGRAM

            Status: Program Scheduling & Development 

            Estimated Completion: Continuous

Additional Information

  • Correspondence
  • Documents
  • Other
    • Actions Authorized by City Council
    • Completed Sewer Projects from 2009 -2013
  • View press releases and other Valdosta News items
Utilities
229-259-3592
229-241-8285
229-434-4132
Director of Utilities
Location

1016 Myrtle Street 
Valdosta, Georgia 31601

Upcoming Events
Repeats every month on the first Friday 48 times.
12/06/2024 - 5:00pm to 8:00pm
01/03/2025 - 5:00pm to 8:00pm
02/07/2025 - 5:00pm to 8:00pm