Engineering Road Projects & Traffic Signal Repairs

Hurricane Helene Updates

Engineering

 

Road Projects (All weather permitting):
  1. Country Club Closure (JWA)
    • Start Date: January 20th
    • Completion Date: 150 days
  2. River Street Closure (RPI)
    • Start Date: TBA
    • Completion Date: 45 days from start date
    • Estimated Timeline: Completed by the end of March
  3. Gornto Closure (Southern Concrete)
    • Start Date: January 8th
    • Completion Date: End of February
    • Progress is moving quickly, and we are hopeful it will be completed by the end of January.
  4. Cypress Closure (Stormwater Division)
    • Start Date: January 15th
    • Completion Date: January 24th
Traffic Signal Projects
  • Baytree/Sustella: Expected completion by the end of February
  • Ann/Williams: Expected completion by the end of February
  • School Flasher on Park Ave (WG Nunn): Expected completion by the end of February
  • Park/Pineview: Expected completion by the end of February
ROW Wire Removal
We have sent requests to telecommunication providers (AT&T and MediaCom) for the removal of wires within the right-of-way and are awaiting their response. Follow-ups are being made, as this delay is hindering street sweeping efforts.
Street Light Outages
  • GA Power: Replacements should be reported via their web link.
  • Colquitt EMC: Replacements should be reported by calling 1-855-293-1804.
  • Alternatively, reports can be directed to the Engineering Department at 229.259.3530, and we will forward them to the appropriate power company.
Engineering
229-259-3530
229-333-1884
City Engineer
Location

Valdosta City Hall Annex
300 N. Lee Street
Valdosta, GA 31601 

Upcoming Events
Repeats every month on the first Friday 48 times.
02/07/2025 - 5:00pm to 8:00pm
03/07/2025 - 5:00pm to 8:00pm
04/04/2025 - 5:00pm to 8:00pm