Capital Projects
- Water Plant No 2 (active construction)
- Project Start Date: on 05/24/23.
- Estimated Project Completion Date: TBD
- Project Status: reviewing the specs for the production wells # 1and 2, reviewing the data specs for the new equipment, drillers on -site in January-February for the production wells installation.
- Dukes Bay New Lift Station/Gravity Sanitary Sewer and Force Main (Active construction)
- Project Start Date: Spring of 2022
- Estimated Project Completion Date: 10/30/23.
- Project Status: Finalizing bullet points that need to be address before closing out the project.
- Knights Creek Emergency Repair (active construction)
- Project Start Date: February 2023
- Estimated Project Completion Date: TBD
- Project Status: emergency pumping ongoing; sewer pipe replacement will occur in late October through November/December
- Exit 16 Valdosta Gateway
- Project Start Date: notice to proceed 06/08/2023
- Project Completed in December of 2023
- Project Status: masonry construction on the signs is ongoing in October and November, landscaping work will occur in November
- Cost: $613,584.40
- Lake Park Rd Culvert Replacement
- Project Start Date: construction began July 2023
- Estimated Project Completion Date: November 2023
- Project Status: utilities relocated, culvert barrel installed, culvert end treatments construction ongoing, road and sidewalk repair scheduled in November
- Cost: $651,978.00
- West Street Sidewalk (anticipated construction)
- Project Start Date: TBD
- Estimated Project Completion Date: TBD
- Project Status: project has been delayed for utility relocations non-city owned; that utility submitted a relocation plan in October 23, and will be proceeding with relocation in late-2023/early-2024
- $1,270,271.20
- Estimated Project Completion Date: late summer 2024
- Project Status: equipment and materials fabrication and delivery will take until early-2024; construction anticipated in spring/summer of 2024
- $1,279,247.20
Project Start Date: Council awarded 06/08/2023
- Gornto & Baytree Traffic Signal & Intersection Improvement (active contract, anticipated construction)
- Project Start Date: Council awarded 06/08/2023
- Estimated Project Completion Date: late summer 2024
- Project Status: equipment and materials fabrication and delivery will take until early-2024; construction anticipated in spring/summer of 2024
- $1,279,247.20 - Awarded to Reames & Sons Construction on 8/24/2023
- Start date has not been determined.
- Old Clyattville (anticipated construction)
- Project Start Date: TBD
- Estimated Project Completion Date: TBD
- Project Status: final design and permitting by state and federal agencies is ongoing
- $5,712,207.32 - Awarded to Reames & Sons Construction on 3/21/2024
- Start date has not been determined
- Dogwood Drive (area improvements)
- Funding Source: SPLOST
- Project Cost; estimated $2M
- Project Start Date: estimated construction start spring 2024
- Estimated Project Completion Date: TBD
- Project Status: project is designed, City Attorney office is completing final property acquisitions
Engineering
229-259-3530
229-333-1884
City Engineer
Location
Valdosta City Hall Annex
300 N. Lee Street
Valdosta, GA 31601
News
12/20/2024 - 10:23am
12/19/2024 - 4:50pm
12/18/2024 - 1:24pm
Upcoming Events
Repeats every month on the first Friday 48 times.
01/03/2025 - 5:00pm to 8:00pm02/07/2025 - 5:00pm to 8:00pm
03/07/2025 - 5:00pm to 8:00pm